Project Brays Home Page About Project Brays Learning Center Frequently Asked Questions Maps and Exhibits Media Room Contact Us Search Terms, Conditions and Notices Regarding Usage Privacy Policy Accessibility Site Map

Project Overview
Project History
Project Highlights
Project Schedule / Status
Project Photos and Renderings
The Partners
Construction Activities Update
April 2013
(Schedule is updated quarterly)

Completed Construction
The following chart highlights construction that has been completed as of April 2013, as well as each project’s total percent completion to date.


Project Segments Complete Total % Complete
Eldridge Road Basin 7 (of 9) 80%
Old Westheimer Basin and
Upstream Channel Modifications
3 (of 3) 100%
Arthur Storey Park Basin 12 (of 12) 100%
Willow Waterhole Basin 3 (of 8) 50%
Channel Modifications 7 (of 12) 56%
Bridges 9 (of 32) 28%

Current Construction
The following construction projects are currently under construction.


Project Segment Start* Finish*
Willow Waterhole Basin
4 (of 8) 1st Quarter 2012 3rd Quarter 2013
Eldridge Road Basin
8 (of 9) 2nd Quarter 2011 2nd Quarter 2013
Eldridge Road Basin
9 (of 9) 3rd Quarter 2012 3rd Quarter 2014

Scheduled Construction Next 6 Months
The following construction projects are anticipated to begin in the next 6 months.
Project Segment Start* Finish*
Bridges
(Wheeler/Lidstone Bridge)
View Detour Plan
10 (of 32) 2nd Quarter 2013 3rd Quarter 2014

*Note: construction schedule is anticipated and subject to change.

Harris County Flood Control District U.S. Army Corps of Engineers