Project Brays Home Page About Project Brays Learning Center Frequently Asked Questions Maps and Exhibits Media Room Contact Us Search Terms, Conditions and Notices Regarding Usage Privacy Policy Accessibility Site Map
Your opinion matters. Take our quick survey.
Project Overview
Project History
Project Highlights
Project Schedule / Status
Project Photos and Renderings
The Partners
Construction Activities Update
January 2011
(Schedule is updated quarterly)

Completed Construction
The following chart highlights construction that has been completed as of January 2011, as well as each project’s total percent completion to date.


Project Segments Complete Total % Complete
Eldridge Road Basin 7 (of 11) 66%
Old Westheimer Basin and
Upstream Channel Modifications
3 (of 3) 100%
Arthur Storey Park Basin 12 (of 12) 100%
Willow Waterhole Basin 3 (of 8) 43%
Channel Modifications 5 (of 12) 18%
Bridges 2 (of 32) 10%

Current Construction
The following construction projects are currently under construction.


Project Segment Start* Finish*
Channel Modifications
(S. Braeswood to Bertner Bridge)
6 (of 12) 4th Quarter 2009 4th Quarter 2011
Channel Modifications
(Ardmore to Holcombe)
View Hike and Bike Detour Plan
View this Segment's Construction Schedule Map
7 (of 12) 2nd Quarter 2010 2nd Quarter 2012
Bridges
(S. Braeswood Blvd.)
3 (of 32) 4th Quarter 2009 4th Quarter 2011

Scheduled Construction Next 6 Months
The following construction projects are anticipated to begin in the next 6 months.
Project Segment Start* Finish*
Eldridge Road Basin 8 (of 11) 2nd Quarter 2011 2nd Quarter 2012
Bridges
(Wheeler/Lidstone Bridge)
4 (of 32) 3rd Quarter 2011 4th Quarter 2012

*Note: construction schedule is anticipated and subject to change.

Harris County Flood Control District U.S. Army Corps of Engineers