Construction Activities Update
July 2008
(Schedule is updated quarterly)

Completed Construction
The following chart highlights construction that has been completed as of July 2008, as well as each project’s total percent completion to date.

| Project |
Segments Complete |
Total % Complete |
| Eldridge Road Basin |
4 (of 10) |
61% |
Old Westheimer Basin and
Upstream Channel Modifications |
3 (of 3) |
100% |
| Arthur Storey Park Basin |
12 (of 12) |
100% |
| Willow Waterhole Basin |
2 (of 8) |
55% |
Channel Modifications
North Bank of Mason Park
(Freshwater Tidal Marsh) |
3 (of 12) |
16% |
Bridges
(Fannin Street Bridge) |
1 (of 32) |
3% |
Current Construction
The following construction projects are currently under construction.

| Project |
Segment |
Start* |
Finish* |
| Eldridge Road Basin |
5 (of 10) |
2nd Quarter 2007 |
3rd Quarter 2008 |
| Eldridge Road Basin |
6 (of 10) |
4th Quarter 2007 |
3rd Quarter 2008 |
Channel Modifications
(Calhoun to Ardmore) |
3 (of 12) |
2nd Quarter 2007 |
3rd Quarter 2008 |
| Willow Waterhole Basin |
3 (of 8) |
3rd Quarter 2007 |
3rd Quarter 2009 |
Scheduled Construction Next 6 Months
The following construction projects are anticipated to begin in the next 6 months.
| Project |
Segment |
Start* |
Finish* |
| Eldridge Road Basin |
7 (of 10) |
4th Quarter 2008 |
4th Quarter 2009 |
Channel Modifications
(Lawndale to OST) |
5 (of 12) |
3rd Quarter 2008 |
4th Quarter 2009 |
Channel Modifications
(Ardmore to Holcombe) |
6 (of 12) |
3rd Quarter 2008 |
4th Quarter 2009 |
Bridges
(S. Braeswood) |
2 (of 32) |
4th Quarter 2008 |
1st Quarter 2010 |
Bridges
(Old Spanish Trail) |
3 (of 32) |
3rd Quarter 2008 |
4th Quarter 2009 |
*Note: construction schedule is anticipated and subject to change.
|
 |
|