Construction Activities Update
January 2010
(Schedule is updated quarterly)

Completed Construction
The following chart highlights construction that has been completed as of January 2010, as well as each project’s total percent completion to date.


Project Segments Complete Total % Complete
Eldridge Road Basin 7 (of 11) 66%
Old Westheimer Basin and
Upstream Channel Modifications
3 (of 3) 100%
Arthur Storey Park Basin 12 (of 12) 100%
Willow Waterhole Basin 3 (of 8) 43%
Channel Modifications
North Bank of Mason Park
(Freshwater Tidal Marsh)
4 (of 12) 12%
Bridges
(Fannin Street Bridge)
1 (of 32) 3%

Current Construction
The following construction projects are currently under construction.


Project Segment Start* Finish*
Channel Modifications
(Lawndale to OST)
5 (of 12) 1st Quarter 2009 1st Quarter 2010
Bridges
(Old Spanish Trail)
2 (of 32) 1st Quarter 2009 2nd Quarter 2010

Scheduled Construction Next 6 Months
The following construction projects are anticipated to begin in the next 6 months.
Project Segment Start* Finish*
Eldridge Road Basin 8 (of 11) 3rd Quarter 2010 3rd Quarter 2011
Channel Modifications
(Ardmore to Holcombe)
6 (of 12) 2nd Quarter 2010 4th Quarter 2011
Channel Modifications
(S. Braeswood to Bertner Bridge)
7 (of 12) 4th Quarter 2009 2nd Quarter 2011
Bridges
(S. Braeswood Blvd.)
3 (of 32) 4th Quarter 2009 4th Quarter 2010

*Note: construction schedule is anticipated and subject to change.