Construction Activities Update
January 2011
(Schedule is updated quarterly)

Completed Construction
The following chart highlights construction that has been completed as of
January 2011, as well as each project’s total percent completion to date.

| Project |
Segments Complete |
Total % Complete |
| Eldridge Road Basin |
7 (of 11) |
66% |
Old Westheimer Basin and
Upstream Channel Modifications |
3 (of 3) |
100% |
| Arthur Storey Park Basin |
12 (of 12) |
100% |
| Willow Waterhole Basin |
3 (of 8) |
43% |
| Channel Modifications |
5 (of 12) |
18% |
| Bridges |
2 (of 32) |
10% |
Current Construction
The following construction projects are currently under construction.

Scheduled Construction Next 6 Months
The following construction projects are anticipated to begin in the next 6 months.
| Project |
Segment |
Start* |
Finish* |
| Eldridge Road Basin |
8 (of 11) |
2nd Quarter 2011 |
2nd Quarter 2012 |
Bridges
(Wheeler/Lidstone Bridge) |
4 (of 32) |
3rd Quarter 2011 |
4th Quarter 2012 |
*Note: construction schedule is anticipated and subject to change.
|
 |
|