Construction Activities Update
April 2013
(Schedule is updated quarterly)

Completed Construction
The following chart highlights construction that has been completed as of April 2013, as well as each project’s total percent completion to date.

| Eldridge Road Basin |
7 (of 9) |
80% |
Old Westheimer Basin and
Upstream Channel Modifications |
3 (of 3) |
100% |
| Arthur Storey Park Basin |
12 (of 12) |
100% |
| Willow Waterhole Basin |
3 (of 8) |
50% |
| Channel Modifications |
7 (of 12) |
56% |
| Bridges |
9 (of 32) |
28% |
Current Construction
The following construction projects are currently under construction.

Willow Waterhole Basin
|
4 (of 8) |
1st Quarter 2012 |
3rd Quarter 2013 |
Eldridge Road Basin
|
8 (of 9) |
2nd Quarter 2011 |
2nd Quarter 2013 |
Eldridge Road Basin
|
9 (of 9) |
3rd Quarter 2012 |
3rd Quarter 2014 |
Scheduled Construction Next 6 Months
The following construction projects are anticipated to begin in the next 6 months.
Bridges
(Wheeler/Lidstone Bridge)
View Detour Plan
|
10 (of 32) |
2nd Quarter 2013 |
3rd Quarter 2014 |
*Note: construction schedule is anticipated and subject to change.
|
 |
|