Construction Activities Update
June 2010
(Schedule is updated quarterly)

Completed Construction
The following chart highlights construction that has been completed as of June 2010, as well as each project’s total percent completion to date.

| Project |
Segments Complete |
Total % Complete |
| Eldridge Road Basin |
7 (of 11) |
66% |
Old Westheimer Basin and
Upstream Channel Modifications |
3 (of 3) |
100% |
| Arthur Storey Park Basin |
12 (of 12) |
100% |
| Willow Waterhole Basin |
3 (of 8) |
43% |
| Channel Modifications |
5 (of 12) |
18% |
| Bridges |
2 (of 32) |
10% |
Current Construction
The following construction projects are currently under construction.

Scheduled Construction Next 6 Months
The following construction projects are anticipated to begin in the next 6 months.
| Project |
Segment |
Start* |
Finish* |
| Eldridge Road Basin |
8 (of 11) |
3rd Quarter 2010 |
3rd Quarter 2011 |
Bridges
(Wheeler/Lidstone Bridge) |
4 (of 32) |
4th Quarter 2010 |
4th Quarter 2011 |
*Note: construction schedule is anticipated and subject to change.
|
 |
|