About Project Brays

Construction Activities Update

As of January 4, 2017

Status

Project Segments Complete Total % Complete Excavation Complete
Eldridge Road Basin 9 (of 9) 100% 8,749,432 cy
Old Westheimer Basin 3 (of 3) 100% 642,306 cy
Arthur Storey Park Basin 12 (of 12) 100% 6,753,880 cy
Willow Waterhole Basin 7 (of 7) 100% 5,478,282 cy
Channel Modifications 9 (of 12) 75% 1,800,000 cy
Bridges 10 (of 32) 31% N/A
Total 23,423,900 cy
Total Spent to Date $324,000,000

Ongoing Construction

Project Segment Start* Finish* Construction Cost (approximate)
Channel Section Bertner to past
Buffalo Speedway
10 (of 12) June 22, 2016 3rd Quarter 2017 $14,200,000
Control Structures
Three upstream basins
DS 19 May 9, 2016 3rd Quarter 2017 $6,500,000
Total $20,700,000

Under Design

Project Segment Start* Finish* Estimated Cost
Structures Willow Waterhole Basin DS 207 2nd Quarter 2017 3rd Quarter 2018 $12,000,000
Channel Modifications, Stella Link to South Rice 11 of 12 3rd Quarter 2017 3rd Quarter 2018 $10,000,000
Galveston RR Bridge (UP) 11 of 32 4th Quarter 2016 1st Quarter 2017 $2,000,000
Calhoun Bridge (TXDOT) 12 of 32 2nd Quarter 2017 1st Quarter 2018 $4,000,000
Total $28,000,000

*Note: construction schedule is anticipated and subject to change.