The future is looking bright!

The Brays Bayou bridges aren’t the only thing under construction – our website is too! Check back soon to stay informed on all things Project Brays.

South Rice Ave Bridge

The South Rice Ave bridge will begin construction in Winter 2020/2021 and is anticipated to be completed in Winter 2021/2022. The bridge project will cost approximately $11,000,000.

Chimney Rock Rd Bridge

The Chimney Rock Rd bridge will begin construction in Winter 2020/2021 and is anticipated to be completed in Winter 2021/2022. The bridge project will cost approximately $11,000,000.

Hillcroft Ave Bridge

The Hillcroft Ave bridge began construction on July 2020 and is anticipated to be completed in Fall 2020. The bridge project will cost approximately $3,300,000.

Stella Link Rd Bridge

The Stella Link Rd bridge began construction in the Fall of 2018 and is anticipated to be completed in Fall 2020. The Stella Link and Ardmore bridge projects will together cost approximately $7,900,000.

Buffalo Speedway Bridge

The Buffalo Speedway bridge will begin construction in Winter 2020/2021 and is anticipated to be completed in Fall 2021. The bridge project will cost approximately $9,500,000.

Greenbriar Dr Bridge

The Greenbriar Dr bridge began construction in the Summer of 2019 and was completed in Summer 2020. The bridge project cost approximately $4,800,000.

Ardmore St Bridge Update 10/26/2020

The opening of the Ardmore Bridge which connects North and South MacGregor Way and is east of Highway 288, has been delayed due to construction quality issues. Unfortunately, the work performed on the bridge did not meet Harris County Flood Control District specifications during a routine inspection.  Work to remedy the construction issues is expected to take 45 days contingent on the absence of weather delays. The work could begin as soon as Monday, Oct. 26 and continue through December. The Flood Control District apologizes for any inconvenience this may cause and appreciates the community’s patience as our contractor works to resolve quality issues that resulted in a delayed opening. We encourage Harris County residents to use the existing detours that are in place diverting traffic to Hwy 288. To view the detour map, please visit the Construction Updates & Detours section of segment 2 on ProjectBrays.org.

Almeda Rd Bridge

The Almeda Rd bridge will begin construction in Winter 2020/2021 and is anticipated to be completed in one year, ending Winter 2021/2022. The bridge project will cost approximately $7,600,000.

Calhoun Rd Bridge

The Calhoun Road Bridge will begin construction in Spring 2020 and it is anticipated that the bridge and channel work will be completed in Winter 2021/2022. The channel work under bridge will cost approximately $500,000.

Ardmore St Bridge

The Ardmore St bridge began construction in the Fall of 2018 and is anticipated to be completed in Winter 2020/2021. The Ardmore and Stella Link bridge projects will together cost approximately $7,900,000.

Forest Hill Blvd Bridge

Construction for the Forrest Hill bridge was completed in Summer 2019. The final cost of this bridge was $5,048,868.24.

Galveston Sub UPRR (Union Pacific Railroad) Bridge

The UPRR (Union Pacific Railroad) bridge will begin construction in Spring 2020 and is anticipated to be completed in Winter 2020/2021. The bridge project will cost approximately $2,900,000.

South 75th St Bridge

The South 75 St bridge will begin construction in Winter 2020/2021 and is anticipated to be completed in Winter 2021/2022. The bridge project will cost approximately $7,700,000.

Lawndale St Bridge

The Lawndale St bridge will begin construction in Spring 2020 and is anticipated to be completed in Winter 2020/2021. The bridge project will cost approximately $7,300,000.

Telephone Rd Bridge

The Telephone Rd bridge will begin construction in Spring 2020 and is anticipated to be completed in Spring 2021. The bridge project will cost approximately $9,000,000.